We run 14 electric 7.5-tonne box trucks out of one yard, and after eight months the trucks have been fine. The problem is the depot. We have 400A service, and chargers for the last four trucks mean a transformer upgrade with a utility queue quoted at 11 months. Running a diesel backup for peak weeks is eating the savings we modelled. How have others handled this? Did you stagger charging with software, lease a second yard, or just pay for the upgrade? Also keen to hear real numbers on